Edgware home batteries: G98, G99 and power cuts explained

Home Comfort Enterprises editorial team · · 5 min read

Quick answer

  • Edgware town centre sits in UK Power Networks' Eastern Power Networks area on both sides of the Barnet and Harrow boundary (UKPN licence-boundary data).
  • Under ENA EREC G98, systems up to 16 A per phase (3.68 kW) are notified before commissioning or within 28 days of it; anything larger needs a G99 application approved before work starts.
  • A 4 kW inverter runs at 17.39 A, just over the G98 line, so many solar-and-battery systems go through G99 (ENA EREC G98 Issue 2).
  • UK Power Networks says it automatically approves home solar and storage where the maximum export, after any export limitation, is under 5 kW.
  • Ofgem's 2024/25 figures for Eastern Power Networks show about 44.6 supply interruptions per 100 customers and about 32.5 minutes lost per customer over the year, as reported.
  • A standard grid-tied battery shuts down when the grid does; it keeps a home running in a power cut only if the system is designed and installed for backup.

Questions this guide answers

Do I need to tell UK Power Networks about a battery in Edgware?
Will a battery keep my Edgware home running in a power cut?
Does it matter whether my Edgware home is on the Barnet or the Harrow side?