Enfield home batteries: G98, G99 and power cuts

Home Comfort Enterprises editorial team · · 5 min read

Quick answer

  • The Enfield town-centre point sits in UK Power Networks' Eastern Power Networks area, about 6.2 km from its London Power Networks area (UKPN and NESO licence boundaries).
  • Under the ENA's G98 rule, generation up to 16 A per phase (3.68 kW) is notified; above that, a G99 application must be approved before work starts, and a 4 kW inverter at 17.39 A is just over the line.
  • UK Power Networks says it automatically approves an application where the maximum export, after any export limitation, is under 5 kW.
  • Ofgem's 2024/25 figures for Eastern Power Networks show about 44.6 supply interruptions per 100 customers and about 32.5 minutes lost per customer over the year.
  • A standard grid-tied battery shuts down when the grid does; keeping circuits running in a power cut needs backup hardware designed in from the start.
  • Enfield's semi-detached houses have a median EPC score of 60, with only 15.2% at band C or above (ONS, records to March 2025).

Questions this guide answers

Do I need to tell UK Power Networks about a battery in Enfield?
Will a battery keep my Enfield home running in a power cut?
Is my Enfield street on UK Power Networks' Eastern or London network?